Check investment incentives in Türkiye and ask whether you can obtain a licence for the proposed premises. Apply for the investment incentive certificate separately. The right location depends on the activity, utilities, transport access and the requirements of the licensing authority.
Before signing a lease or ordering machinery, confirm which activities the facility can accommodate and when you can apply for investment support.
Investment location and workplace licence
Ask the competent authority whether it can license the premises for your activity. Check zoning, fire safety, environmental conditions, electricity capacity and access for deliveries. A business that requires a workplace opening and operating licence must obtain it before operating (Workplace Licensing Regulation, art. 6).
Compare an organised industrial zone (organize sanayi bölgesi) with other locations. A lower rent may come with higher power connection or transport costs. Ask the owner who will pay for structural changes and agree how the lease will work if the authority delays or refuses approval.
Investment incentives and eligible costs
An eligible project may receive VAT relief on qualifying machinery, customs duty relief, reduced tax or employment support. The investment activity, location, programme and minimum investment size help determine what is available (Presidential Decision No. 9903, arts. 3–5 and 13–17).
Make a budget at ordinary prices and then model the support you can apply for. Separate machinery, building work, hiring and working capital. Check each cost against the certificate rules and the timetable.
Applying for investment incentives
The authorised user files through the Electronic Incentive Implementation and Foreign Investment Information System (E-TUYS). Prepare the activity code, facility address, capacity, budget and domestic or imported equipment list (Communiqué No. 2025/1, arts. 6–7). The investment incentive certificate service sets out the application documents and follow-up records for E-TUYS.
The certificate cannot cover investment expenditure you incur before applying (Decision No. 9903, art. 5/6). Ask how the authority treats a deposit or binding order before you sign it. If the equipment changes later, check the need for a certificate amendment before buying the replacement.
Coordinating permits, orders and expenditure
Put the licensing application, incentive filing, equipment order and planned production start on one calendar. A manufacturer considering two sites can ask each authority to confirm whether the activity fits and obtain installation quotes for both addresses. Tie each payment to its supplier quote, equipment list and approved budget.
Frequently asked questions
Does an incentive certificate authorise the factory to operate?
Apply to the competent licensing authority for permission to operate. Keep the licensing file and investment support file separate.
Can the equipment list be changed?
Check the procedure for changing the certificate through E-TUYS before committing to a different machine.